Article 38/14. Conditions for submission
Section 5. – Modifications of the contract
The contracting body or contractor wishing to rely on one of the revision clauses referred to in Articles 38/9 to 38/12 must make known in writing the facts or circumstances invoked on which it relies, within thirty days either after they occurred or after the date on which the contractor or the contracting body should normally have become aware of them.
Amended byIngevoegd bij KB 2017-06-22/01, art. 21 (in force 30-06-2017)